|
Advent Unpublished White Paper (2/99) by DA Horvath, PE
Evolution of the Nuclear Industry's Environmental Qualification Program
1. Environmental Qualification Background and Brief Description
Environmental qualification is evidence in the form of auditable
documentation demonstrating that equipment will be capable of performing its required
safety function at any time during its installed life under specified service conditions
(including the harsh environment effects resulting from a design basis event).
Nuclear plant designs typically entail use of independent redundant
trains of safety-related systems in order to assure safety function fulfillment
in the event of a single active failure affecting one of the trains [e.g., IEEE
279 which exists as a regulatory requirement but no longer as a current industry
standard. IEEE 279 has been superseded by IEEE 379 and 603]. The purpose of EQ is
to assure that equipment can perform its safety function(s) with no failure mechanism
that could lead to common cause failures or loss of both trains from postulated
service conditions. Therefore, even if both trains of a safety-related system are
exposed to an accident-produced harsh environment, EQ helps to assure operability
of both trains; if a single active failure affects one train, EQ helps to assure
operability of the remaining train. The purpose of EQ is not to prevent all failures
and, in particular, not to prevent random postulated single failures. The primary
role of environmental qualification is to provide reasonable assurance that environmental-
and age-related common failure modes will not occur during performance of safety
function(s) under postulated service conditions. [These statements are consistent
with early and present versions of IEEE 323 as well as IEEE 627.]
Qualification, in general, is demonstration that equipment meets
design requirements (including operability). Therefore, seismic qualification would
provide evidence of operability during a design seismic event. The term equipment
qualification is often used to designate that a piece of equipment is both environmentally
qualified and seismically qualified. [Note: In general, the NRC tends to use the
term environmental qualification and IEEE standards tend to use the broader term
equipment qualification and the synonymous term design qualification.]
As discussed and clarified below, the terms Class 1E and EQ are
not interchangeable and neither associated group of equipment is a subset of the
other. As defined in the IEEE standards, Class 1E equipment or systems are those
electrical components which are essential for achieving emergency reactor shutdown,
containment isolation, reactor core cooling, containment and reactor heat removal,
or prevention of significant release of radioactive material to the environment.
2. Brief EQ History
Figure 1 is a timeline of EQ Program events over the past 30
years. EQ Program requirements in the nuclear industry have evolved in several large
and small steps, in response to many types and degrees of regulatory activities,
and along more than one path and dimension. However, most of these events and effects
can be grouped into five major chronological phases discussed below. These are:
- assuring operability during accident environmental conditions
- addressing aging and margin
- action on intervenor petitions to strengthen EQ requirements (initiation
of formal utility programs)
- EQ Rule (10 CFR 50.49) and follow-up activities
- utility EQ Program refinement for long term maintenance

FIGURE 1 EQ PROGRAM DEVELOPMENT TIMELINE
a. Operability During Accident Environmental Conditions
Early efforts on EQ [e.g., reactor vendor test reports on essential
motors and process instrumentation testing] were specifically directed at assuring
operability of equipment essential for accident mitigation with recognition that
such equipment may be subjected to elevated temperature, pressure, and humidity/steam
conditions as a result of the accident. Later, a concern on operability during and
after exposure to chemical spray and integrated radiation dose was also recognized.
[Sections 5.3.1 and 5.3.2 of the NRC Division of Operating Reactors (DOR) Guidelines,
and as examples, later reactor vendor reports on environmental testing of engineered
safety feature-related equipment] Evolution of requirements to assure accident operability
developed along two paths (industry standards and regulator driven).
In a fashion similar to many other industries, the commercial
nuclear industry considers itself to be self-regulating. This self-regulation takes
the form of industry produced codes, standards and guides which are prepared by
senior level professionals and subject to consensus vote by the applicable professional
society (for example, the Institute of Electrical and Electronics Engineers or IEEE).
Standards are used for safety and to protect users and the environment.
In the 1960s, the industry began debating and converging on agreement
for the need for addressing EQ in one or more industry standards. The result was
the establishment of a requirement for EQ in IEEE Standard 279-1968 and later an
interim use standard devoted entirely to EQ requirements (IEEE 323-1971).
In parallel with industry debates and discussions on EQ, the
Atomic Energy Commission (predecessor of the Nuclear Regulatory Commission), was
preparing its draft and later final general design criteria (GDC) for eventual incorporation
into the Code of Federal Regulations Part 50, Appendix A. These general design criteria
identified the need to assure operability of safety related equipment for accident
mitigation.
Also in parallel, at least two US reactor vendors, were incorporating
accident environment operability requirements into plant design criteria and/or
equipment procurement specifications.
During the late 1960s and early 1970s, EQ requirements were met
by performing tests of equipment prototypes or other samples in test chambers where
the environmental conditions could be raised and lowered accordingly. As discussed
above, in many of the early cases, the test specimens were subjected to only elevated
temperatures and pressures. Later, it was recognized that radiation dose and chemical
spray were also environmental parameters of concern. This recognition caused the
earlier EQ test programs to be considered incomplete and resulted in cases where
the radiation dose and chemical spray concerns were addressed by tests of separate
equipment samples or by analyses. Such approaches were later considered inconclusive.
b. Addressing Aging and Margin
The industry had long awaited the issue of IEEE 323-1971 even
though it was labeled by IEEE as an interim use standard. Many equipment vendors
had orders or pending orders with an EQ requirement specified or expected. The urgency
to provide EQ documentation as part of product delivery was acute. It was well known
that the lack of a standard had already caused prior incomplete or inadequate EQ
tests to be performed and consequently much money was wasted. A typical EQ test
program could cost the test sponsor fifty to two hundred thousand dollars per equipment
type to complete. The release of this standard provided the "perceived promise"
of a consistent pre-approved industry accepted EQ Program test approach. Therefore,
many equipment manufacturers eagerly adopted the use of IEEE 323-1971, not only
for use in testing but also to tout in their marketing literature. They then aggressively
proceeded to initiate costly EQ testing programs.
Unfortunately, even as IEEE 323-1971 was going to press, it was
recognized that it was inadequate in at least two areas: aging and margin. [p. 6
of the NRC's Memorandum and Order dated May 23, 1980] Aging could cause a previously
unforeseen EQ-related common cause failure as follows. Aging leads to degradation.
If two redundant trains of safety-related equipment are aged in a similar fashion
and at similar rates, then both trains of equipment could be near end of operable
life when subjected to the severe environment "shock" of an accident at a time when
called upon to perform an essential safety function. Therefore, it was argued that
if an EQ Program tested a brand new piece of equipment and the equipment passed,
no assurance existed that that equipment and its opposite train counterpart if subjected
to a sufficient amount of aging degradation would be able to perform the required
accident mitigating safety function. [surmised from EPRI NP-1558 A Review of
Equipment Aging Theory and Technology September 1980 and Advent staff experience]
Also, IEEE 323-1971 did not require that a test facility impose
margin on the environmental parameters calculated to be representative of a design
basis accident. Without margin, it was argued that if a testing facility tests an
equipment sample at the same value as the analyzed (predicted or expected) environmental
parameters, test instrument calibration error and production variations could cause
the test results to be non-conservative.
Many members of the IEEE Working Group responsible for IEEE 323
were aware of the new wave of testing being conducted using IEEE 323-1971 and were
anxious to correct the aging and margin deficiencies as well as other less significant
shortcomings in the standard. The result was that a newer version (IEEE 323-1974)
was issued within three years. Typical standard revision cycles are five years or
more. IEEE 323-1974 corrected the earlier aging and margin deficiencies as well
as provided additional guidance and flexibility. IEEE 323 also imposed EQ Program
requirements on all Class 1E equipment, not just those items of equipment subjected
to the harsh environment effects of an accident.
Many nuclear equipment manufacturers objected to the release
of IEEE 323-1974. After expending significant amounts of money testing to IEEE 323-1971,
they were understandably wary of undertaking an even more expensive test program.
[author's personal observation.]
The result was that in the 1970s, up to three EQ test program
variations (different in scope and degree) existed at each of the nuclear plant
facilities including PBNP. These were:
- Early EQ Programs (predating IEEE 323 guidance programs and often lacking
radiation and spray as well as aging and margin qualification) undertaken by
the plant's reactor vendor
- IEEE 323-1971 (which typically lacked aging, margin, and other details)
- IEEE 323-1974
c. Action On Intervenor Petitions to Strengthen EQ Requirements and Initiation
of Formal Utility EQ Programs
Amidst (and possibly in response to) the turmoil of the changing
industry self-imposed requirements, a Nuclear plant intervenor organization called
The Union of Concerned Scientists (UCS) petitioned the NRC on two occasions
(on November 4, 1977 and May 2, 1978) for emergency and remedial relief in the form
of nuclear plant shutdowns until it could be shown that EQ concerns were adequately
addressed.
The NRC responded with two Orders (on April 13, 1978 and May
23, 1980) to nuclear plant licensees. In these orders the NRC acknowledged that
the UCS had highlighted "an area of regulatory review which had not been adequately
addressed," and concluded that mass plant shutdowns were not required, but directed
its staff to take actions to improve licensee EQ Programs.
The NRC staff consequently issued several regulatory documents
of increasing scope, priority, and threat of enforcement action. In these documents,
the NRC directed and provided criteria (NRC DOR Guidelines and NUREG 0588) for comprehensive
and regimented reviews of EQ Programs as well as detailed individual equipment qualification
evaluations. The NRC also required that summary results be submitted for regulatory
review and that licensees prepare justifications for continued operation (JCO) for
any uncovered EQ Program deficiencies. The result was that the first formal EQ Programs
were initially developed.
d. 10 CFR 50.49 (EQ Rule) and Follow-up Activities
To assure that continuing adequate attention was provided to
licensee EQ Programs, the NRC undertook rulemaking for a change to the Code of Federal
Regulations. On January 21, 1983, 10 CFR 50.49 was issued mandating requirements
for an EQ Program. This rule had several major effects including:
- grandfathering previous EQ efforts completed prior to DOR Guidelines and
NUREG 0588
- requiring an upgrade to the rule's requirements for replacement equipment
- expanding accident scope from just pipe breaks to all design basis events
producing a harsh environment
- defining a post-accident mild environment
- expanding equipment scope from just safety-related to include post-accident
monitoring instruments and certain non-safety-related equipment with adverse
failure modes
- specifying additional considerations for aging and synergistic effects
- establishing a final deadline for completion of qualification efforts
In 1984, the NRC prepared SERs for each plant's EQ Program based
on submittals received from licensees. Each SER committed to follow on-site inspections
for EQ Program compliance. In 1985, the NRC undertook five pilot licensee EQ Program
inspections (one in each of the then five regions) as part of an effort to develop
consistent review guidelines. Within a few years after the EQ Rule deadline for
qualification, all licensees received a site inspection of their EQ Programs. These
inspections included not only numerous reviews of the paperwork auditability trail
used to establish qualification of various equipment types, but also walk-down inspections
to confirm adequacy of the equipment installation's EQ configuration. (For example,
EQ Pilot Inspections of Calvert Cliffs, Crystal River, Zion, Fort Calhoun, and Rancho
Seco).
e. Refinement of EQ Programs for Long Term Maintenance
After the EQ Rule's final deadline (November 30, 1985) for meeting
EQ requirements had passed, the NRC continued to take an active interest in EQ through
the monitoring of EQ problems identified by licensees through LERs and other processes.
Many EQ related NRC Information Notices were released in subsequent years to notify
nuclear utilities of EQ problems identified elsewhere which might prove more generic
in nature. Sometimes the problems resulted from new testing conducted and other
times from a closer look or independent review performed on existing documentation.
Utility EQ Programs had been developed quickly because of the
need to meet what were found to be aggressive schedule requirements. Often conservative
decisions were made because they were quicker and required less evaluation. As a
result, the decisions were often later found to not be cost-effective.
Therefore, as a result of reviewing NRC released EQ problems
and lessons learned at other plants and a desire to improve both cost effectiveness
and long term usability, many utilities performed evaluations and undertook efforts
to improve their EQ Programs. Examples of improvement areas include:
- EQ equipment list and associated basis (what equipment should really be
on the list?)
- EQ equipment maintenance requirements including maintenance intervals (what
maintenance is really necessary?)
- EQ equipment obsolescence problems (what parts will be needed to maintain
an EQ configuration but are no longer available?)
- normal service condition temperatures (what is the normal daily and seasonal
temperature variation as compared to the design normal maximum temperature which
may have been used in the qualified life evaluations?)
- EQ file compilations (in what way can this EQ package be compiled to facilitate
future reviews, references by others, and plant modifications?)
- accident environmental conditions including effects of steam flooding (what
are more reasonable expected accident environment conditions as a function of
plant location?)
More recently the NRC has identified EQ as an unresolved safety
issue not only for components (such as cables for long term license renewal), but
also because of reluctance shown by many utilities to upgrade their DOR Guideline
qualified equipment to the newer requirements of 10 CFR 50.49. Questions within
IEEE standards committees and at the NRC still exist on whether existing approaches
to aging and qualified life are acceptable. Because EQ continues to be an important
regulatory issue, a knowledge and understanding of the bases behind the many EQ
Program decisions which have been made continue to be important.
Please contact us if you
are interested in other ways that Advent can provide additional information or training
on the complex and multidimensional aspects of Environmental Qualification.
|